Key points
- A complete design basis prevents costly changes later.
- Site, utilities, environmental limits and safety spacing shape the design early.
- Long-lead equipment and bid packages should be defined before EPC engagement.
A new process facility is a major investment. Many of the factors that determine whether it will be safe, profitable and easy to operate are fixed during the earliest stages of process design. Considering them early avoids redesign and protects the project budget and schedule.
1. A complete, agreed design basis
Define capacity, turndown, feedstock and product specifications, design margins, operating philosophy and expansion allowances. Ambiguity here is one of the most common sources of late scope changes.
2. Site conditions and outside battery limits (OSBL)
Ambient temperature ranges, cooling water quality, available utilities, access, soil and neighbouring facilities all influence the process design. OSBL items such as utility supply, storage, effluent treatment and flare systems are often underestimated in early estimates.
3. Utilities
Steam, power, cooling, nitrogen, instrument air and fuel demands should be quantified from the heat and material balance and matched to supply. Utility shortfalls discovered late are expensive to correct.
4. Process safety from the start
Inherently safer design — minimizing hazardous inventories, moderating conditions and simplifying the process — is most effective at the concept stage. Preliminary hazard identification (HAZID), relief system philosophy, plant layout and spacing, and area classification should be addressed early rather than added later.
5. Environmental performance
Estimates of air emissions, effluents and waste streams developed during process design feed into permitting and the design of pollution-control systems. A preliminary environmental assessment helps avoid surprises.
6. Long-lead equipment
Large compressors, reactors, specialty columns and certain heat exchangers can take many months to fabricate. Identifying and specifying them early protects the schedule.
7. Cost estimates and economics
Budget-level capital and operating cost estimates, developed from a defined process scope, support sound capital appropriation decisions.
8. Bid packages before EPC engagement
When the owner defines the process scope before bidding, EPC proposals can be compared on a consistent basis and the owner keeps control of key process decisions.
Bringing the pieces together
These considerations come together in a front-end engineering package. Binhashim Technologies coordinates with PEI, which provides process design services from feasibility and conceptual studies through FEED, for new projects in Pakistan.